Elle
Hi
I'm trying to say a tasks is resourced like this
"PMO[63.5%];Other[25%];PM[12.5%]"
but it's telling me "this is not a valid units value"
if i take the decimals out it works, yet on the error message it actually
says I can have up to 2 decimal places...
What am I doing wrong?
Thanks