John,
I've been reading the Microsoft paper "Create a Project Plan in 5 Easy
Steps"
(
http://office.microsoft.com/en-ca/project/HA011361531033.aspx#Step 1 ).
If I have a shcedule that is driven by regulatory deadlines (i.e., specific
data must be calulated and reported to a regulatory oversight board by X
date) certain of my tasks must be completed by a specific business day in
order to be submitted to the next (dependent) step so that the ultimate
regulatory filing submission date is satisfied. Therefoe, it would seem I'd
want to set up the project such that each step along the way to satisfying a
regulatory filing submission date has a fixed end date (i.e., it must be
completed by a specific date in order for the next step or dependency to
occur on time). Somewhere in the article I was reading, I thought I read
that there are two scheduling approaches: 1) work-based or "effort-driven"
(in which one enters the amount of hours that will be required to complete
the tasks. The assignment of resources to these tasks causes the Duration
(i.e., the elapsed time it will take to complete the tasks) to be calculated,
and 2) duration-driven approach, which is strictly a scheduling approach
(i.e., elaped time to perform work is pre-set by setting duration for the
task and then resources are assigned to the task). I'm not really clear on
this latter approach (it sounds as if you have a task in a duration-driven
approach, and your duration is pre-set to 3 days, you simply assign the
appropriate staff to the task for the hours the duration requires?).
From what you've said, I would use a "Fixed Duration" setting for the Tasks,
if I wanted to use a Duration-driven approach (i.e., set the duration and
then assign enough resources to satisfy the duration time requirement). And
if I wanted to use an effort-driven approach (the default in Project), I
would use a "Fixed work" setting for the tasks, then assign my resources, and
Project would tell me when each task would be completed (based on how many
resources I assigned and at what % committment).
I probably am a bit unclear about the two scheduling approaches. I'd
appreciate any clarity you can bring to my understanding, perhaps by stating
how each of these two scheduling approaches would impact the
regulatory-deadline-based project I mentioned.
I very much appreciate your thoughtful responses.