Tad Campbell
All tasks have a constraint type of ASAP.
When, I try to change the start date on it, it will not change. It goes
back to the original date. It tells me there is a constraint or task
conflict but it does not exist.
When I set predecessors for tasks after it (same level), it does not
calculate the dates.
I have outdent the task above the subtask and change the date, it all works
properly. I indent it and it works fine. This was an ok workaround. But,
it is not the right way.
Does anyone know why this is happening?
When, I try to change the start date on it, it will not change. It goes
back to the original date. It tells me there is a constraint or task
conflict but it does not exist.
When I set predecessors for tasks after it (same level), it does not
calculate the dates.
I have outdent the task above the subtask and change the date, it all works
properly. I indent it and it works fine. This was an ok workaround. But,
it is not the right way.
Does anyone know why this is happening?