Question reg managing resource allocation on a Project

S

Sushant

Hello –

Scenario
A resource was previously 100% on the project and assigned to various tasks.
Today it was told that the resource will only be available 50% to the
project. What is the easy to rectify this, without having to go into the
project plan and adjust the resource allocation to all the tasks assigned?
 
J

Jim Aksel

You can go to the Resource Usage sheet. Insert the column "assignment
units". Change the assigned units from 100% to 50%. This will change the
duration of all tasks where this resource is assigned unless they are fixed
duration tasks. It can be accomplished in about 1 minute since all the tasks
are in the same place and you can drag the 50% down.

If a change in duration is not acceptable, make all the tasks Fixed Duration
prior to your change. You will have to manually substitute a different
resource to make up for the unavailability of the original resource work
hours, or change the scope of the work so it can be done within the new
smaller amount of work allotted. (Cost, Schedule, Performance ... pick two).
---
If this post was helpful, please consider rating it.

Jim
It''s software; it''s not allowed to win.

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top