Reg Calendar view

  • Thread starter siddharth.bhattacharya
  • Start date
S

siddharth.bhattacharya

Hi All,

I have a mpp file with columns like Task, Task name , Duration, Start
date , Finish date Application etc.

Now when I change from the GNATT view to CALENDAR view I am only shown
the task description and the duration. I only want the selected columns
like Application to appear in the calendar view. Is there an option
that will give me a customized view.

Any help would be of great help.
 
J

JulieS

Hi Sid,

I'm not sure what the "Application" information is that you see in the
Gantt chart view table. Is this text typed into a Text field?

You can change the information displaying in the bars in the Calendar
View under Format > Bar Styles. Select the bar (noncritical, critical,
etc.) In the Fields choice select the Text1 field -- or whatever field
you have entered the "Application" information in.

I hope this helps. Let us know how you get along.

Julie
 