relative start/stop times

H

Hans

Hi,

I would like to have a column in my table view which gives the start and
stop times (in days) of the tasks relative to the start date of the project.
The purpose is to give a planning not related to absolute dates but related
to the "zero-date" of the project.

Thanks,

Hans
 
J

Jan De Messemaeker

Hi,

You can insert a custom duration field containing a formula.
If you want the days to be calculated as per the project calendar use the
function ProjDateDiff
Else use DateDiff
ProjectStart is an available field for the formulae.
Hope this helps
 
H

Hans

ProjDateDiff works like a charm! I tried the DateDiff earlier but that gave
"#ERROR" in every field.

Thanks,

hans
 