G
Gary
One of my project managers has created a project that has her resources
tasked out for the duration of the year. These tasks are not contingent on
eachother, however they are to be completed simultaneously. This project has
the resources working 20 + hours a day. How do I fix this over allocation
without skewing the finish date to 2013. In reality these tasks take 14
weeks at the most and start as soon as we get a work order from the customer.
These tasks are close to the actual start dates plus or minus a few days. I
changed the units percentage as well as the work hours, but I still get
overallocation.
Microsoft Project 2003 Professional
tasked out for the duration of the year. These tasks are not contingent on
eachother, however they are to be completed simultaneously. This project has
the resources working 20 + hours a day. How do I fix this over allocation
without skewing the finish date to 2013. In reality these tasks take 14
weeks at the most and start as soon as we get a work order from the customer.
These tasks are close to the actual start dates plus or minus a few days. I
changed the units percentage as well as the work hours, but I still get
overallocation.
Microsoft Project 2003 Professional