Resource Graph over-allocation

P

pominoz

Hi

I am using MS Project to plan production in a manufacturing environment (not
ideal I know but it is the only tool I have).

I have come accross a problem that has me stumped when using the resource
graph.

The scenario is I have a task that takes 16 hours, allocated to one resource
and I have entered a duration of 2 days (we work an 8 hour day, therefore my
calendar is set to 8 hours). When I view this resource on the resource graph
it shows 16 hours per day, and there is no other work allocated to it.

I want the resource graph to show the work evenly, i.e. eight hours per day.
Alternativley if the task took 14 hours it should show 8 hours on day 1, and
six hours on day 2.

I would be delighted if someone can help me with this as it is really
hurting my brain (and my boss is annoying me about it!).

Thanks in advance

John
 
J

Jan De Messemaeker

Hi Pominoz,

There are so many small problems I could imagine, but none is immediate.
It would be much faster if you send me the file
Decypher my address or find it on my website...

Greetings
 
J

Jan De Messemaeker

To the curious:
Problem solved.
Two problems:

1. Resource graph did not show work but peak units,
2. And in the assignment of the resource units had received the work value.
 