G
GTS
Hi all,
I'm new to Project, so bear with me.
I am setting up a schedule for a future project, which will start within a
year.
The dilemma is that the project has a number of tasks that must be done at
the last minute (the project is a show). We have tasks at the beginning of
the endeavor and have anticipated lag time so that everything will ready for
the big scramble at the end just before the show. After that, there are
removal tasks that can be done at leisure.
The last minute tasks have dependencies and resources associated with them.
They are only associated with the tasks at the beginning in that all those
need to be done before the last-minute tasks start.
I know it's not recommended to try to schedule backward and forward in the
same project, but I don't know if there is a way to schedule this kind of
scenario without making it so complicated that we can't make changes as the
project progresses.
The "late as possible" constraint pushes the tasks to the end of the project
(makes sense). Is there a way to say "as late as possible but before this
other task"?
A co-worker suggested setting the tasks up with a start-to-finish constraint
with the predecessors moving backward from the deadline date. Is this a good
idea?
How would you approach it?
I'm new to Project, so bear with me.
I am setting up a schedule for a future project, which will start within a
year.
The dilemma is that the project has a number of tasks that must be done at
the last minute (the project is a show). We have tasks at the beginning of
the endeavor and have anticipated lag time so that everything will ready for
the big scramble at the end just before the show. After that, there are
removal tasks that can be done at leisure.
The last minute tasks have dependencies and resources associated with them.
They are only associated with the tasks at the beginning in that all those
need to be done before the last-minute tasks start.
I know it's not recommended to try to schedule backward and forward in the
same project, but I don't know if there is a way to schedule this kind of
scenario without making it so complicated that we can't make changes as the
project progresses.
The "late as possible" constraint pushes the tasks to the end of the project
(makes sense). Is there a way to say "as late as possible but before this
other task"?
A co-worker suggested setting the tasks up with a start-to-finish constraint
with the predecessors moving backward from the deadline date. Is this a good
idea?
How would you approach it?