D
Devendra Bhagat
I have shared resources between two projects. For one particular task there
are going to be 2 different resources working at different time. For. e.g.
One resource would be working from 01/09/2003 to 07/11/2003. The second
resource would work from 04/12/2003 for 25 days. I achieved this by
assigning the task to these 2 resources. One of the resource i.e Resource 1
has left the organisation on 10/11/2003. So in the Resource availability, I
have specified, that Resource 1 would be available for this project from
start date to 10/11/2003. When I add the additional work to be done by
Resource 2 it shows resource 1 to overallocated. How do make this resource
inactive. I am not using Project Server.
are going to be 2 different resources working at different time. For. e.g.
One resource would be working from 01/09/2003 to 07/11/2003. The second
resource would work from 04/12/2003 for 25 days. I achieved this by
assigning the task to these 2 resources. One of the resource i.e Resource 1
has left the organisation on 10/11/2003. So in the Resource availability, I
have specified, that Resource 1 would be available for this project from
start date to 10/11/2003. When I add the additional work to be done by
Resource 2 it shows resource 1 to overallocated. How do make this resource
inactive. I am not using Project Server.