Shift complete schedule to the right

V

Varun Malhotra

We are in the planning stages of our project. I had created an intitial
schedule from the WBS and now need to move the complete schedule to start at
a later date. I tried to change the project start date under "Project
Information", but that doesnt help me.

I want to be able to shift the whole schedule towards the right to start a
month later and not effect the activity durations at all.

I am sure that its simple. Any help is appreciated.

Thanks,
Vm.
 
C

Cristina Pupper

I always create a Project Start milestone and have all the starting tasks
have the milestone as a predecessor. That way I can change the start date of
the milestone and everything is shifted forward.

Hope that helps!
 