Showing only tasks that end this week

M

Meg

Hi,

I thought I used to do this in old versions of Project, but I only use
Project like once a year, so I can't be sure.

I want to show all tasks that are due this week and can't figure it out. I
tried filtering with a date range, but that doesn't seem to work. In fact I
can't even figure out what the purpose of that filter is!

Does anyone know how to do this?
 
D

DonL

Meg,

Try using the following custom filter:

A/O Field Name Test Value
--------------------------------------------------------------------------------------------
Finish Is greater than or equal to "Finish Week
Beginning Date"?
And Finish Is less than or equal to "Finish Week
Ending Date"?
And Actual Finish Equals NA
And Summary Equals No
And External Equals No

Hope this helps! :)
 