E
edie
when the project is updated, tasks that are delayed (no actual start date)
automatically are updated with the date that is baselined and a percentage is
calculated and displayed. if the complete date is delayed, the actual
complete date is filled in with the baseline completion date and the
percentage is at 100%. I would like for unfinished tasks to have there actual
start date to remail n/a and the percentages to remain. Please help.
automatically are updated with the date that is baselined and a percentage is
calculated and displayed. if the complete date is delayed, the actual
complete date is filled in with the baseline completion date and the
percentage is at 100%. I would like for unfinished tasks to have there actual
start date to remail n/a and the percentages to remain. Please help.