Task as place holder - no date

M

Mike Glen

Hi Jess,

Welcome to this Microsoft Project newsgroup :)

No, sorry. Why not use a milestone with zero hours and then just change the
date when you need to?

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 
J

JulieS

Hi Jess,

Sorry no. Project is a scheduling tool and as such shows dates for all
tasks. A milestone task (0 duration) will show the same start and end
date/time, but non-the-less will still show a date.

If you want to just "hide" the date, you could change the font color to
white.

Perhaps if you tell us more about what you are trying to do, we can assist
further.

Hope this helps. Let us know how you get along.

Julie
 