F
fxs
How would I add a "Project Management" task to my project such that it
starts on the day the project starts, and ends on the last day of the
project (ends with the task 44)?
I tried putting in 1SS in the predecessor for my Project Management task -
that works fine...
But, when I change it to "1SS, 34FF" (implying start with Task1, End when
the last task #34 finishes), it resets the start & finish date to match
those of task 34.
Any thoughts on how you would do this?
starts on the day the project starts, and ends on the last day of the
project (ends with the task 44)?
I tried putting in 1SS in the predecessor for my Project Management task -
that works fine...
But, when I change it to "1SS, 34FF" (implying start with Task1, End when
the last task #34 finishes), it resets the start & finish date to match
those of task 34.
Any thoughts on how you would do this?