task linking and successor dates

W

wjBigSax

When I link two consecutive tasks, project automatically sets the start date
for the second project to start the following day after the first completes.

How can I automatically get the second task to start on the same day the
first completes? I don't want to deal w/ negative lag days to accomplish
this.

thanks
 
J

Jan De Messemaeker

Hi,

In fact it makes it start the following MINUTE.
But when the predecessor ends exactly at the end of a working day, the
succesor starts at the beginning of working time the next day!
 