I work in the I.T. Infrastucture field and have many projects that have most
of the effort done during the work week (M-F) but do have to execute major
changes during our change control period, currently 12 hours on Sunday. Is
there a way to idendify our tasks that need ot occur on a Sunday? I know
that I can apply a constraint but that creates more work when something
changes in the plan as someone has to manually go through the project to
change the constraints to the appropriate Sunday.