Tasks without Actual Start Date but should have started.

D

DMM

Hi,

Sorry for all the questions. I am trying to find a report, view or table
which will show all tasks which should have started by today but have NA for
the actual start date.
 
J

JulieS

Hi DMM,

Take a look at the filter "Should Start by...". You could apply that to a
view and print.

Hope this helps. Let us know how you get along.
Julie
 