T
Terry Montgomery
Greetings,
I have been asked to include several "preliminary" tasks in our project plan
templates that are predecessors to the actual start date of our installation
projects. These would be sales and contract signing tasks. I establish the
install Kickoff date as the offical start date for MS Project. I then insert
a new task as the first task in the Gantt view as a predecessor task to the
Kickoff task. I assign it a "Finish to Start" relationship to the Kickoff
task and give it a negative lag time to set the date prior to the Kickoff
project start date. The question is, when I open the Project Information
dialog box it shows the correct date I want in the "Start Date" field but if
I click on the Statistics button the Start Date in that window shows the date
of the predecessor task. So which one is MS Project actually using to
calculate the project timeline?
Thanks,
Terry Montgomery
I have been asked to include several "preliminary" tasks in our project plan
templates that are predecessors to the actual start date of our installation
projects. These would be sales and contract signing tasks. I establish the
install Kickoff date as the offical start date for MS Project. I then insert
a new task as the first task in the Gantt view as a predecessor task to the
Kickoff task. I assign it a "Finish to Start" relationship to the Kickoff
task and give it a negative lag time to set the date prior to the Kickoff
project start date. The question is, when I open the Project Information
dialog box it shows the correct date I want in the "Start Date" field but if
I click on the Statistics button the Start Date in that window shows the date
of the predecessor task. So which one is MS Project actually using to
calculate the project timeline?
Thanks,
Terry Montgomery