J
JenW
I apologize, I'm new to MSP- so this could be something easy that I just
can't seem to do. I am using MSP to track our projected work load for 2006 -
each column is a week and I have several hundred tasks set up (I have to file
a report via a gantt chart). I need to find an easy way to track how many
tasks are active in a particular week. Example - task 193 runs for four
weeks in January - for each of those weeks, how many other tasks are also
running? I've got to project how much revenue we can expect in a particular
week, what resources we'll need, etc.
Thanks in advance.
can't seem to do. I am using MSP to track our projected work load for 2006 -
each column is a week and I have several hundred tasks set up (I have to file
a report via a gantt chart). I need to find an easy way to track how many
tasks are active in a particular week. Example - task 193 runs for four
weeks in January - for each of those weeks, how many other tasks are also
running? I've got to project how much revenue we can expect in a particular
week, what resources we'll need, etc.
Thanks in advance.