Y
Y
Hi,
I wonder how to model the following two problems in MS Project?
1. Simultaneous resource assignments require more than one
resources to be available and work on an task at the same
time. The resources may have different
calendars/availability but need to have the same work
contour on the task.
2. Constrain two tasks start at the same time. But it seems
Project does not allow either
P -> S and S -> P or,
P -> S and P -> S.
Thanks.
I wonder how to model the following two problems in MS Project?
1. Simultaneous resource assignments require more than one
resources to be available and work on an task at the same
time. The resources may have different
calendars/availability but need to have the same work
contour on the task.
2. Constrain two tasks start at the same time. But it seems
Project does not allow either
P -> S and S -> P or,
P -> S and P -> S.
Thanks.