Dear Smarf -
In Gantt Chart view, MS Project does not provide any field just to show the
lag between current task and its predecessors.
Instead, you can split the Gantt Chart view (Choose Window, Split) to
display the Task Form view at the bottom of Gantt Chart.
By default, the Task Form view would display only the resource assignment
and predecessor information of the currently selected task in Gantt Chart.
Predecessor table would show the name of the predecessor with dependency type
and lag as separate columns
If you would view other information of the currently selected task, then
right click on the Task Form and choose the appropriate option.
If my suggestion helps, please consider rating my reply. Thanks!
--
Regards
Sai [PMP]
* Enjoy scheduling with Microsoft Office Project *
smarf said:
Is there a column that just shows the lag time between a task and its
predecessor?