D
Dave Shultz
My objective is to provide an enterprise view where the background format is
yellow for all tasks which are < 100% cmplt and where Finish is prior to
today's date. I would like the view to be dynamic so that the date criteria
is not a fixed date but will automatically update to the current day’s date
whenever the plan is opened. I’m using Project Server 2007.
yellow for all tasks which are < 100% cmplt and where Finish is prior to
today's date. I would like the view to be dynamic so that the date criteria
is not a fixed date but will automatically update to the current day’s date
whenever the plan is opened. I’m using Project Server 2007.