My objective is to provide an enterprise view where the background format is
yellow for all tasks which are < 100% cmplt and where Finish is prior to
today's date. I would like the view to be dynamic so that the date criteria
is not a fixed date but will automatically update to the current day’s date
whenever the plan is opened. I’m using Project Server 2007.
 
J

Jan De Messemaeker

Hi,

From what you write I suppose you can create a formula in a custom field.
Create a yes/No formula in a flag field (say Flag1)
Then create a filter (say F1Filt) with flag1 equals Yes as the condition
Now creata view by copying theview you have in mind, and edit it to open
with that filter and teh checkbox "Highlight filter" ON
Finally, in Format, Text Styles, set teh background for "highlighted tasks"
to yellow.

HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
M

Mike Glen

Hi Dave,

Try posting on the microsoft.public.project.server newsgroup (forum).
Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and
other useful Project information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top