D
Darlene
We want to use Project 2002 timesheets to capture all of a
resource's time. I.e., Project related tasks, nonworking
time, and non-project (work) related tasks. It's obvious
how to record time for projects and nonworking time, but
we need some suggestions on how to best record time
against non-project related tasks (overhead).
A number of our resources work on a combination of project
and non-project related tasks. It's important to track
ALL time so project managers have a true picture of a
resource's availability. For example, a resource is
working 50% on a non-project related task, therefore
he/she is only available 50% of the time to work on a
project. (Note: it's not a simple as adjusting the
resources availability in global settings because the
percent varies.)
To capture this non-project time we've considered:
1. Using Outlook's nonworking time.
2. As non-project tasks come up have resources create a To
do lists and then promote the list to a project plan when
required.
3. Create an "Overhead Tasks" project plan that all
resources are assigned to. Time would be recorded against
the various tasks as required.
Any comments and/or suggestions?
Darlene
resource's time. I.e., Project related tasks, nonworking
time, and non-project (work) related tasks. It's obvious
how to record time for projects and nonworking time, but
we need some suggestions on how to best record time
against non-project related tasks (overhead).
A number of our resources work on a combination of project
and non-project related tasks. It's important to track
ALL time so project managers have a true picture of a
resource's availability. For example, a resource is
working 50% on a non-project related task, therefore
he/she is only available 50% of the time to work on a
project. (Note: it's not a simple as adjusting the
resources availability in global settings because the
percent varies.)
To capture this non-project time we've considered:
1. Using Outlook's nonworking time.
2. As non-project tasks come up have resources create a To
do lists and then promote the list to a project plan when
required.
3. Create an "Overhead Tasks" project plan that all
resources are assigned to. Time would be recorded against
the various tasks as required.
Any comments and/or suggestions?
Darlene