M
MDI Tammy
My schedule includes late start and finish dates however, on some of the late
start/finish dates they are way off base.
Example: start finish late start late finish
3/28/04 4/4/04 9/1/04 9/9/04
other dates are okay just some are way off. How can I fix this problem? I
am still building my schedule.
Thanks
start/finish dates they are way off base.
Example: start finish late start late finish
3/28/04 4/4/04 9/1/04 9/9/04
other dates are okay just some are way off. How can I fix this problem? I
am still building my schedule.
Thanks