K
Kevin
I'm working with Project 2000 for the first time, and I'm
wondering if I should be linking summary tasks or not.
For example, before we design a project, we go through a
planning phase. All tasks in the planning phase must be
completed before the design phase begins. I have two
summary tasks: Planning and Design, with multiple subtasks
under each.
Is it OK to just list the summary task "Planning" as a
predecessor to the summary task "Design"? I tried exactly
this, and it seems to screw up what Project 2000 shows as
my critical path. None of the tasks show up in the
critical path after I do this. I believe it's because I'm
linking these summary tasks.
Can anybody shed some light on how to handle these
situations?
Thanks!
wondering if I should be linking summary tasks or not.
For example, before we design a project, we go through a
planning phase. All tasks in the planning phase must be
completed before the design phase begins. I have two
summary tasks: Planning and Design, with multiple subtasks
under each.
Is it OK to just list the summary task "Planning" as a
predecessor to the summary task "Design"? I tried exactly
this, and it seems to screw up what Project 2000 shows as
my critical path. None of the tasks show up in the
critical path after I do this. I believe it's because I'm
linking these summary tasks.
Can anybody shed some light on how to handle these
situations?
Thanks!