C
CGull
I have a simple schedule of about 30 tasks where I have a task (A) that is
linked to a previous task (B) via a FS predecessor link. The start date on
the task sheet is correct for task (A) but when the gantt chart is displayed
it preceeds task (A) with a series of dots. There are no contraints
associated with task (A) and it previously had been linked to task (B) via a
FF predecessor link. I have other similar situations in the schedule which I
can't seem to clear up. What am I doing wrong?
Any help would be apprciated
linked to a previous task (B) via a FS predecessor link. The start date on
the task sheet is correct for task (A) but when the gantt chart is displayed
it preceeds task (A) with a series of dots. There are no contraints
associated with task (A) and it previously had been linked to task (B) via a
FF predecessor link. I have other similar situations in the schedule which I
can't seem to clear up. What am I doing wrong?
Any help would be apprciated