F
Fernando
Hi.
i want to do something like that:
one resource A (a person) working morning and afternoon.
one resource B (an equipment) working only afternoon
some tasks (type 1) which need resource A and B together
other tasks (type 2) which just need resource B.
i've programmed it with a calendar for A (morning and afternoon) and
other calendar for B (just afternoon), then i assign task type 1
resources A and B (100% each), and tasks type 2 only resource B (100%).
But then project doesn't understand that B (the equipment) must work
with A, and it program so i can see in the resource chart that in a task
type 1 sometimes is only working A, other times is only working B
(imposible!!) and other times are working them both.
how can a do it well?
thanks
i want to do something like that:
one resource A (a person) working morning and afternoon.
one resource B (an equipment) working only afternoon
some tasks (type 1) which need resource A and B together
other tasks (type 2) which just need resource B.
i've programmed it with a calendar for A (morning and afternoon) and
other calendar for B (just afternoon), then i assign task type 1
resources A and B (100% each), and tasks type 2 only resource B (100%).
But then project doesn't understand that B (the equipment) must work
with A, and it program so i can see in the resource chart that in a task
type 1 sometimes is only working A, other times is only working B
(imposible!!) and other times are working them both.
how can a do it well?
thanks