Tools/Tracking/Update Project

C

Catfish Hunter

After moving the status date task that had a start (but not completed), the
end date moved to the right as it should. But task that did not start did not
move to the right past the status date. Where is the option I need to turn on?
 
J

John M.

Do you happen to have a constraint on the task that was not updated?
Several of the constraints (e.g. must start on, start no later than) can
cause tasks to not be updated by this feature.

John M.
 
C

Catfish Hunter

I have turned off the option to have task honor their constrants. Should this
work? I did look and these task I refer to have a start no earlier constrant.
 